Proj Overview

PROJECT OVERVIEW

A Design-Build Approach to Military Housing

When the Naval Facilities Engineering Command needed new military housing capable of accommodating 336 beds in under three months, Tindall knew that coordination and proper planning would be mission critical. For this design-build project, the precaster’s engineering and field operations departments worked closely with the designer, general contractor, and erector to address the owner’s needs and develop a total precast solution that would exceed expectations.

PRECAST SOLUTION

This five-story, 83,377-square-foot dorm required progressive collapse construction and placement of MEP under the ground-level precast floor. To overcome these challenges, Tindall took a design-build approach to the project’s design and carefully coordinated each step of the erection to deliver the most efficient and cost-effective structure possible. The final design leveraged insulated precast walls with integral architectural finishes, columns, beams, and precast slabs for both the floors and roof.

The Bachelor Enlisted Quarters featured 83 units with four beds each, an inviting common area, and an attractive exterior comprised of architectural precast, reveals, and sills. Tindall’s close collaboration with the other teams on the project was critical to delivering this structure on time and within budget.

“Tindall’s on-site supervision and ability to respond timely to issues or concerns is second to none. Tindall did an outstanding job on making our schedule and doing whatever was necessary to assure that the next critical path activity was not delayed, and the schedule was maintained.” – Jeff Mallow, Field Operations Manager, Harkins Builders

 

Awards_
There are no records.
Project Team

Architect & Engineer

Stantec Architecture

Contractor

Harkins Builders

Owner

Naval Facilities Engineering Command

Precaster

Tindall Corporation

Key Project Attributes

  • New construction of a five-story 83,377 sq. ft. total precast structure
  • Insulated precast walls with an architectural thin brick finish
  • 83 units totaling 336 beds

Project/Precast Scope

  • This is an all-precast building including precast solid wall panels, insulated wall panels, transfer beams, double tees, and flat slabs
  • Tindall’s design-build total precast concrete approach efficiently addressed the need for progressive collapse accommodations and allowed a 336-bed military barrack to be erected and dried-in in less than four months