Proj Overview

Project Overview

Froedtert Health and the Wisconsin Athletic Club partnered to create a state-of-the-art sports medicine and fitness facility for communities around Menomonee Falls, Wis.

The building had to combine needs for aquatic and other fitness needs for WAC, as well as sports-medicine and orthopedic services for Froedtert.

Precast Solution

The 90,000-square-foot facility was clad with 175 precast concrete insulated sandwich wall panels using several finishes to create an aesthetically pleasing appearance and reduce the scale of the building.

The WAC portion consists of 47,500 square feet of space on one floor devoted to an aquatic center with two indoor pools, a whirlpool, and an outdoor lap pool, along with a gym, training studio, three group exercise studios, fitness areas, and locker rooms. It also includes 5,000 square feet of restaurant space.

Froedtert’s section consists of 42,500 square feet of space on two floors offering a variety of sports-medicine and orthopedic facilities.

Precast was chosen for its speed of construction, according to Jeremy Olivotti, vice president of preconstruction for Mid-States Concrete Industries. “Precast could offer flexible space to adjust as needs change,” he says.

“The high-end finish and R-values were a couple benefits that also helped make precast the system of choice.” The panels feature 3 inches of EPS insulation sandwiched between an exterior 3-inch architectural wythe of concrete and an interior 3.5-inch structural wythe.

The panels feature an architectural finish using colored concrete with sandblasting and a water-wash finish. No challenges arose in casting or erecting the panels, he notes, as all issues were anticipated and worked out upfront in the preconstruction phase.

 

Awards_
There are no records.
Project Team

Architect:

Eppstein Uhen Architects

Engineer:

Pierce Engineers

General Contractor:

Ryan Companies

Owner:

Village of Monomenee Falls, Wis.

Precaster:

Mid-States Concrete Industries

Precast Specialty Engineer:

Mid-States Concrete Industries

Key Project Attributes

  • Sports medicine and fitness center combine needs to create combined 90,000-square-foot building.
  • Wisconsin Athletic Club portion consists of 47,500 square feet of space on one floor devoted to an aquatic center with two indoor pools, a whirlpool, and an outdoor lap pool, along with a gym, training studio, three group exercise studios, fitness areas, and locker rooms. It also includes 5,000 square feet of restaurant space.
  • Froedtert Health’s section consists of 42,500 square feet of space on two floors offering a variety of sports-medicine and orthopedic facilities.
  • Located on 10.6 acres on corner of major traffic corridor in city.

Project/Precast Scope

  • 175 wall panels, encompassing 37,385 square feet.
  • Panels feature an architectural finish using colored concrete with sandblasting and a water-wash finish.
  • Speed of construction was key factor in specifying precast.