PROJECT OVERVIEW
Google’s new headquarters for thousands of employees in New York, N.Y., at St. John’s Terminal was constructed with innovation as a key component of the building’s interior and exterior design. The massive St. John’s Terminal, which spans two city blocks in lower Manhattan, consists of the building’s original three stories topped with nine new levels. This expansion to 12 stories, along with the need for two high-rise elevator cores, necessitated a unique design that would ensure that the existing structure could support the added load of steel framework and cast-in-place concrete floors.
BRIDGE BUILDING TECHNIQUES SAVE TIME AND MONEY
Working alongside Rizzani de Eccher (RDE), Jersey Precast developed a precast concrete building core with Lego-style connections. Collectively, the companies decided on match-casting for the core, an approach commonly used in bridge construction where each precast concrete element is cast against the previous one. By using this technology, extremely tight tolerances could be achieved while also mitigating error. The precast concrete core was built just like a bridge span but oriented vertically instead of horizontally.
George Hand II, Jersey Precast CEO, says that 298 segmental precast concrete units were manufactured to create the core. The units had a maximum weight of 84 tons (76 tonnes) and were about 29 ft 8 in. (9 m) long by 13 ft 6¾ in. (4 m) wide by 10 ft 4 in. (3 m) tall. In addition to the elements needed to build the core, Jersey Precast also provided 114 precast concrete stairs, 153 stair landing slabs, and 55 elevator landing slabs.
Using one trade “to furnish, install and erect a precast system with a steel system, the initial savings was in cranage. We only had two cranes on this entire structure. For a building of this size, it could easily handle four to five cranes if there was a subcontractor doing the core. That alone delivered several million dollars worth of savings for the project,” says Dave Pisacrita, Metropolitan Walters principal, the steel and core erector on the project. |