PROJECT OVERVIEW

The Bakery Tower is a 13-story total precast apartment complex in Richmond, Virginia's Arts District, delivering 211 residential beds in a dense downtown urban environment. The 170,000 SF structure measures 142'-4" long by 88'-2" wide. Also constructed on-site and separated by a firewall is a 150-stall precast parking garage with on-grade retail and office space.

PRECAST SOLUTION

Tindall Corporation provided a total precast concrete system for the Bakery Tower utilizing their proprietary T-SLAB® flooring system — a product engineered for the long spans and load demands of mid-rise residential construction. The structural system is complemented by insulated exterior wall panels serving dual structural and architectural functions, interior corridor walls, stair and elevator boxes, and full precast stair units — a fully integrated precast package from floor to façade.

The exterior panels feature multiple finish types and mix colors, with medium and heavy sandblasting producing a varied, textured aesthetic across the building's elevations. The adjacent 150-stall parking garage was also delivered in precast, erected separately and divided from the residential tower by a firewall.

Tindall's experience in complex urban precast systems allowed the team to offer the client a cost-effective, fast-to-revenue solution — the tower was erected in approximately three months, the garage in two and a half. Built in a constrained downtown Richmond site, single-crane erection was employed throughout, requiring precise piece sequencing coordinated across both structures.

Take the Video Tour

 

Awards 
There are no records.
Project Team

Owner / Developer

SWA Development

PCI-Certified Precast Producer

Tindall Corporation

Architect

SWA Architects-VA Inc.

General Contractor

SWA Construction

Key Project Attributes

  • Total precast system — T-SLAB® floor/roof, insulated structural/architectural exterior walls, interior corridor walls, stair and elevator boxes, and precast stairs
  • Multiple finish types and mix colors — medium and heavy sandblasting delivering a varied, textured exterior across all elevations
  • Tower erected in approximately 3 months; adjacent 150-space precast parking garage erected in 2.5 months
  • Single-crane erection across both structures due to constrained downtown Richmond site
  • Insulated exterior wall panels serve dual structural and architectural roles — no secondary cladding system required

Project/Precast Scope

  • 13 Stories
  • 170,000 SF of Precast
  • 823 total precast pieces: 396 T-Slabs (14"), 199 insulated wall panels (12"), 92 wall panels (8"), 6 wall columns, 20 beams, 10 shear walls, 27 stair boxes, 59 stairs, 10 cornices, and 4 flat slabs
  • Erected October 23,2023 - January 29, 2024