PROJECT OVERVIEW

The Brownsburg High School Fieldhouse project included 44,364-SF of architectural precast wall panels featuring three thin-brick types, cladding a striking 80,000-SF fieldhouse addition with a bow-truss roof. Designed to expand the school’s athletic and community facilities, the new fieldhouse accommodates an eight-lane indoor track and multiple basketball courts, providing a highly functional and flexible space for students and the broader community.

The addition was designed to integrate seamlessly with the existing high school campus. Three thin-brick colors were incorporated into the precast panels to closely match adjacent masonry construction, with distinctive architectural profiles concentrated within the lower 10 feet of the façade. A defining feature of the structure is the bow-truss roof system, which required radiused precast end panels to precisely follow the roof’s curvature and enhance the building’s dynamic visual expression.

Close coordination across the project team ensured that the non-load-bearing precast panels established the building enclosure early in the construction process. This approach enabled efficient sequencing while delivering a durable exterior solution.

PRECAST SOLUTION

Architectural precast concrete was selected to meet the project’s complex geometric conditions, construction sequencing requirements, and aesthetic goals. A total of 225 insulated wall panels were used, including large-format panels measuring up to 11 feet 6 inches wide by 52 feet 7 inches tall and weighing up to 60,000 pounds. All panels were required to be erected and fully braced prior to installation of the bow-truss structural steel roof system, making precast an ideal solution for schedule reliability and structural stability.

Because the roof trusses extended beyond the exterior face of the wall panels, the precast units were fabricated with integrated pockets to accommodate the structural steel. High Concrete Group worked closely with the structural engineer and steel contractor to ensure pocket sizes and elevations were accurately detailed, enabling precise alignment and efficient field installation.

Precast delivered additional value through early collaboration during the design development phase. High Concrete Group assisted in converting the east elevation column covers from hand-set masonry to approximately 4,400 square feet of thin-brick precast column covers. This modification eliminated the need for a separate masonry supplier and accelerated the construction schedule by approximately three weeks, reinforcing precast concrete as a solution that provides architectural consistency, construction efficiency, and long-term durability.

 

Project Team

Architect

CSO

Engineer

Lynch, Harrison & Brumleve, Inc.

Contractor

Meyer Najem Construction

Owner

Brownsburg Community School Corporation

Architectural Wall Panel Precaster

High Concrete Group, LLC

Structural Precast Seating Riser Precaster

AVAN Precast Concrete

PCI Certified Erector

Ben Hur Construction Co.

Key Project Attributes

  • The project consisted of an 80,000-square-foot fieldhouse in addition to an existing school, featuring an eight-lane indoor track and multiple basketball courts.
  • Although the wall panels were non-load-bearing, all panels were required to be erected and fully braced prior to the installation of the bow-truss structural steel roof system.
  • All bow trusses extended beyond the exterior face of the precast wall panels, which required the incorporation of pockets in the panels and close coordination with the structural steel engineer to ensure the correct pocket sizes and elevations were achieved.
  • To match the bow-truss roofline, all end wall panels featured a radiused top, with some panels measuring as large as 11 feet 6 inches wide by 52 feet 7 inches tall and weighing up to 60,000 pounds.
  • Three different types of thin brick were required to match the architectural profile of the existing school.
  • During the early consultation process, High Concrete Group assisted in changing the East Elevation column covers from hand-set brick to 4,400 square feet of thin-brick precast column covers to match the precast walls, which eliminated the need for an additional supplier and saved the general contractor approximately three weeks of construction time.

Project/Precast Scope

  • 44,364 SF of Architectural Insulated Wall Panels with 3 types of thin-brick
  • Number of Precast Panels: 225
  • Erection Time: Six (6) Weeks
  • 400 SF of Structural Precast Risers (78 pieces) for interior seating