Proj Overview

PROJECT OVERVIEW

New five-story building doubles the number of service providers of old facility, larger pharmacy, larger laboratory, and expanded services, including an onsite MRI suite. New and improved building is more sustainable, more convenient, and more architecturally pleasing.

Read more about this project in the Fall 2019 issue of Ascent.

PRECAST SOLUTION

Clark Pacific reduced the number of contractors considerably by being responsible for the entire building envelope under their scope of work.

 

Awards_
There are no records.
Project Team

Designer

HOK

Structural Engineer

John A. Martin & Associates

Contractor

Rudolph and Sletten Inc.

Owners

Kaiser Foundation Health Plan

Precast Concrete Producer

Clark Pacific

Key Project Attributes

  • Precast concrete was the ideal solution to meet the U.S. Army’s blast requirements.
  • Precast concrete bulb tees made it possible to span the building with one precast concrete member.
  • The barracks are flanked by smaller precast concrete support structures.

Project/Precast Scope

  • 251,800 sf of space
  • Five-story building includes lightweight precast concrete panels.