Project Team

PCI-Certified Precast Concrete Producer:

Shockey Bros., Inc.

Key Project Attributes

  • Completed in 1972.
  • The design was completed in the year of the release of the 1st edition of the PCI Design Handbook when the governing code was ACI 318-64

Project/Precast Scope

  • Garage was constructed before durability and resilience were in the thoughts and recommended practice of the industry.
  • Open bay framing using single tees developed by T.Y. Lin and slender precast concrete columns to provide greater openness than spandrel beams.
  • The area totals 106,300 sf in two bays with a total length of 327 ft.