Project Team

Architect: 

Weidner Architecture LLC

Engineer: 

Apex Structural LLC

Contractor:

 Woodruff Construction

Owner:

Delaware County 

Precaster:

Advanced Precast Company

Precast Specialty Engineer:

Beton-Stahl 

PCI Certified Erector:

Cedar Valley Steel 

Key Project Attributes

  • A black mix design was used for the building’s exterior panels Jail Cells
  • Sandblasting and acid washing allowed for an even rock exposure across the totality of the building.

Project/Precast Scope

  • 27,315 square foot, two-story building
  • 213 precast concrete panels
  • The precast concrete exterior shell was erected in eight days