Project Overview

The USCG Pier November Recapitalization project involved the complete demolition and reconstruction of Pier November to provide the United States Coast Guard with a modern, resilient marine facility capable of supporting current and future operational requirements. The project centered on the construction of a new deep-foundation-supported pier designed to withstand the demanding marine environment while providing long-term structural reliability. The foundation system was a critical component of the project, requiring careful planning and execution to address challenging subsurface conditions, environmental restrictions, and logistical constraints within an active waterfront setting.

Visually, the project transformed an aging waterfront structure into a robust marine facility supported by hundreds of driven piles extending beneath the harbor floor. Following demolition of the existing pier, specialized marine construction equipment operated from barges and crane-mounted pile driving rigs to install the new foundation system. The work took place over soft coastal sediments commonly known as “pluff mud,” underlain by the dense Cooper Marl formation that ultimately provided the bearing support for the structure. The resulting pier consists of a uniform grid of deep foundations supporting the deck and fender systems, creating a durable platform capable of serving Coast Guard operations for decades.

Construction required innovative approaches to overcome site limitations and maintain production efficiency. Temporary pile storage and assembly areas were established on portions of the existing pier to reduce waterfront congestion and streamline material handling. The project also incorporated environmentally responsible construction practices, including the use of biodegradable hydraulic oils, turbidity controls, noise mitigation measures, and compliance with environmental restrictions intended to protect sensitive marine species and habitats throughout construction.

Precast Solution

Precast concrete piles were selected as the foundation system because they provided the optimal combination of structural capacity, durability, constructability, and cost efficiency for the project’s geotechnical conditions. Compared to alternative systems such as steel pipe piles, the 24-inch square precast concrete piles offered superior resistance to the aggressive marine environment while delivering the required load-bearing performance. The prefabricated nature of the piles also enhanced quality control, reduced field construction time, and minimized material waste. In addition, the driven pile system allowed for dynamic load testing and immediate verification of pile integrity and hammer performance during installation, providing confidence in the long-term performance of the foundation.

A total of 466 precast concrete piles were installed, consisting of 358 bearing piles supporting the pier structure and 108 fender piles protecting the facility from vessel impacts. To successfully install the piles through the soft upper soil layers and into the underlying Cooper Marl, steel stingers ranging from 20 to 40 feet in length were attached to the pile tips. Twenty-foot stingers were primarily used along the perimeter of the pier, while 40-foot stingers were utilized for interior piles where additional guidance and stability were required. These stingers provided improved alignment and directional control during driving, significantly increasing installation accuracy and productivity.

The strategic use of precast piles and stingers enabled the project team to overcome difficult soil conditions while maintaining production rates, ensuring that the foundation system met all structural requirements and was delivered safely, efficiently, and within project constraints.

 

Awards 
There are no records.
Project Team

Owner: United States Coast Guard

PCI-Certified Precast Concrete Producer: Standard Concrete Products, Inc.

Engineer of Record: Moffat & Nichol

General Contractor: Whiting-Turner Sub: Russell Marine LLC

Key Project Attributes

  • High load Bearing Capacity
  • Durability in marine environment
  • Quality Control and consistency
  • Construction efficiency
  • Cost effective
  • Verifiable performance
  • Environmental Benefits

Project/Precast Scope

  • 466 24" Square precast prestresed concrete piles