There was a problem loading this area.
Project Team

Architect

SCI Architects

Owner

City of Fishers, Ind.

Contractor

AECOM Hunt

Structural Engineer

Fink, Roberts, Petrie Inc.

Precast Concrete Producer/Photo Credit

CORESLAB Structures (INDIANAPOLIS) Inc.

Key Project Attributes

  • The city needed the seating bowl, which is designed to seat 7500 people, to be flexible and also wanted it to mimic the sight lines used at the downtown Indianapolis home of the Pacers.
  • Coreslab worked with the structural steel contractor to meet an accelerated building schedule that would have the entire event venue substantially built by the end of 2024.

Project/Precast Scope

  • With the aggressive construction schedule, precast concrete had to be erected at night, while workers erected steel during the day.
  • It took only six weeks to erect all the precast concrete, with in-factory fabrication taking about four months.
  • The typical span of the riser units was 30 ft. The seating bowl features Coreslab’s structural gray concrete with form finish bottoms and trowel top finishes to ensure both durability and a sleek aesthetic.